The Exposure Clock: Who Pays for a Grid Upgrade if the Data Center Never Opens?

In this brief’s illustrative $250 million upgrade, a Virginia GS-5 data center with the maximum credit reduction posts $135 million of collateral. By year three about $106 million of it remains, against $330 million of remaining modeled cost. If the customer defaults then, about $224 million, or 68% of that cost, is uncovered by the collateral. In the model, nothing is billed before service.

That is modeled exposure, not a forecast, built on terms the Virginia State Corporation Commission (SCC) adopted. This brief traces who carries it at each stage and ends with two asks. I have not repeated the contract terms in Juncture’s benchmark of 27 large-load terms or the show cause orders in our FERC large-load review.

What Virginia adopted

On November 25, 2025, the SCC created GS-5 for customers with at least 25 megawatts (MW) of measured or contracted demand on a contiguous site and a load factor of at least 75%. The class takes effect January 1, 2027; its contract and collateral provisions apply to customers who take initial service and sign an electric service agreement on or after that date. The terms:

  • a 14-year contract, with a load ramp of up to four years;
  • minimum monthly charges of 85% of contracted distribution demand, 85% of transmission demand and 60% of generation demand;
  • an exit fee for outstanding minimum charges over the remaining term if the customer ceases operations or defaults, reduced if another customer takes the capacity;
  • collateral of $1.5 million per MW, reducible by up to 70% based on established credit, with one-fourteenth released each year;
  • a free cut of up to 20% of contracted capacity, and a further 30% only if another customer assumes it, each on 36 months’ notice.

The SCC did not decide how exit fee revenue will be treated in rates.

The Exposure Clock

Exposure moves through three windows. In each, a different instrument is supposed to protect ratepayers, a gap sits in it, and a different group pays if it fails. The payer column is my judgment.

Window Instrument Named gap Named payer
Pre-service Construction letter and contribution in aid of construction (CIAC) The order text I reviewed does not say when minimum bills begin or when collateral is posted relative to construction spending Retail customers
In-service The 85% transmission minimum It pays the zone’s general transmission rate, not the specific upgrade Zonal customers
Exit Exit fee and collateral Collateral is reduced up to 70% and released yearly; exit fee revenue treatment is undecided Wholesale customers

The clock is reusable. For any large-load tariff, ask what protects ratepayers in each window and who pays when it does not.

The illustrative upgrade

These are my assumptions, not Dominion’s costs or rates.

  • A data center contracts for 300 MW of GS-5 service.
  • Its load triggers a $250 million local transmission reinforcement in Dominion’s zone, separate from direct-connect facilities.
  • Recovery costs 12% of capital a year, or $30 million, equal to $8.33 per kilowatt-month of contracted demand.
  • Ignore discounting and the load ramp. Billing begins at customer service. No capacity is reassigned.

Window one: pre-service

Dominion’s public construction-letter template provides for delay and cancellation payments, but liability depends on the signed agreements and the facilities they cover. On October 29, 2026, Dominion filed its proposal in PUR-2026-00131: a CIAC for direct-connect transmission facilities and proportionate cuts in construction collateral for CIAC paid. It applies prospectively and to direct-connect facilities, so a local reinforcement like the one modeled sits outside it. In the model, a load that arrives two years late leaves up to $60 million (2 years x $30 million) uncovered, with $0 billed before service.

Window two: in-service

In the model, the customer’s minimum bills fund the upgrade. In the SCC’s July 31, 2026 Rider T1 order, as I read it, the 85% transmission minimum enters the allocation of Dominion’s PJM transmission costs among classes. It pays the zone’s general transmission rate, not this upgrade. The figures below are therefore the amount the specific upgrade carries if not otherwise recovered.

Case Customer pays Modeled amount carried
Uses 150 MW of 300 MW $25.5 million a year (85% of 300 MW) $4.5 million a year (15%)
Free 20% cut to 240 MW $20.4 million a year (85% of 240 MW) $9.6 million a year (32%)

Window three: exit

Suppose the developer fails in year three with 11 years left. Remaining modeled cost is 11 x $30 million = $330 million. Modeled transmission minimums are 11 x $25.5 million = $280.5 million, owed only if collected.

Collateral is $450 million before reduction (300 MW x $1.5 million). With the maximum 70% reduction it is $135 million. After three years 11 of 14 parts remain: about $106 million.

Year-three collateral Remaining Share of $330 million
With 70% credit reduction $106.1 million 32%
Without reduction $353.6 million 107%

With the reduction, about $223.9 million of the $330 million is uncovered, assuming the collateral is the only recovery and all of it goes to this upgrade. Collateral applied to other obligations would leave less. Against the modeled minimums, the shortfall is $174.4 million.

The cost can then move beyond Virginia retail rates. FERC’s June 18, 2026 order in Docket EL26-67 reports commenters’ point that a retail large-load tariff protects the utility’s retail customers but may not protect other wholesale transmission customers. FERC also said that when upgrade costs enter a transmission owner’s revenue requirement and load does not arrive, other transmission customers may pay more. The SCC directed Dominion to work with Old Dominion Electric Cooperative and other electric distribution companies on zonal cost assignment, with an update due within 120 days of July 31, about November 28, 2026.

Where federal rules stand

FERC preliminarily identified minimum contributions and sought a mechanism to credit payments. On November 16, 2026, PJM filed its Fast Energization proposal (ER27-531), which would require a transmission owner cost recovery agreement and full readiness deposits with each application. In ER27-520 (filed November 16, 2026, accession 20261116-5300), the transmission owners request March 16, 2027 for new service rates and an indeterminate effective date for the cost recovery agreement. As summarized in public commentary on the filing, the filed agreement proposes a minimum contribution of 80% to 100% of a firm transmission service benchmark and stage-based charges for pre-service termination. Comments were due 7 December 2026 per the Federal Register notice; FERC’s 18 November errata notice (accession 20261118-3051) extends the comment period, reportedly to 15 January 2027.

Two asks (my judgment)

  • Comments in ER27-520 (originally due 7 December 2026 per the Federal Register notice, 91 FR 74550; FERC extended the comment period in an 18 November errata notice, eLibrary accession 20261118-3051, reportedly to 15 January 2027) should seek zonal crediting of cost recovery agreement payments, so that a payment toward a transmission owner’s revenue requirement reduces what other customers in the zone carry.
  • The SCC should cap the collateral credit reduction where the customer has posted no contribution, whether in PUR-2026-00131 or in the GS-5 compliance tariff, before the January 1, 2027 effective date. Credit should be earned by money posted, not by balance-sheet standing alone.

My prediction: the GS-5 compliance tariff will take effect on January 1, 2027 with the 70% credit reduction uncapped. If the SCC caps it before then, this call is wrong.

Limits

All dollar figures come from my illustrative model and ignore discounting and the ramp. I could not retrieve Dominion’s filed GS-5 tariff, so its collateral units and applicability are unverified, and I use the November 2025 order’s terms. Neither the order text I reviewed nor the model settles when minimum bills and the term begin.