Tenaga Nasional Berhad (TNB), Malaysia’s grid utility, has signed supply agreements for 59 data center projects totalling 8.3 gigawatts (GW) (The Star, 13 Jul 2026). As of August 2026, data centers were drawing 1,374 megawatts (MW) of the 2,346 MW contracted, or 58.6% (Malay Mail, 4 Nov 2026). The ministry calls reserved but unused capacity “phantom demand” but did not say how much of the 41.4% gap is speculation rather than ramp-up.
Malaysia added rules on commitment, water and approvals after its boom began; Latin America is at the start of that path. This brief offers a five-link chain for judging grid-access regimes, prices the gap, and names open proceedings.
How Johor happened
TNB offered faster connections. Its Green Lane cut connection time from 36 months to “as little as 12” (The Star, 28 May 2026). A July 2025 category priced data center power at about 60 sen per kilowatt-hour, per analysts (EdgeProp), against a 45.40 sen average base tariff (Energy Commission).
Rules came later:
- Commitment. Operators file 10-year plans, and access is released in phases under binding supply agreements (Malay Mail). In November 2025, the deputy minister reported June utilization of roughly 47% and an 85% target (Hansard). TNB’s general terms bill new customers’ monthly peak shortfalls against an 85% reference for four years and 75% for two more (TNB). Press reports say data center agreements carry one too (w.media). Eligible high-voltage customers with zero assessed connection charge post a refundable charge equal to 25% of TNB’s project cost, forfeited if they miss demand targets (TNB).
- Water. Johor said it would stop approving Tier 1 and 2 data centers over water (The Star, 26 Nov 2025). Its assembly also reported a water benchmark with no time basis, so I do not treat it as a standard (Johor Assembly).
- A freeze. In February 2026 the Prime Minister said new non-AI data center applications had been restricted for about a year and a half (Malay Mail).
The reservation chain
Every grid-access regime sells a reservation: a promise of future load that someone builds against. If the load does not come, someone pays. Five links decide who. For each, ask whether a rule exists before the first large request. A reservation gap flags underuse. Ramp schedules and contracts help establish its cause and who pays. A guarantee can protect the build schedule yet leave idle capacity unpaid. “None found” means none in public sources.
| Link | Malaysia | Latin America (public evidence) |
|---|---|---|
| 1. Screen: who may reserve? | Phased access; 10-year plans | Brazil: competitions where requests exceed available capacity (Decree 12.772/2025). Colombia: UPME windows, January and May (Res. 443/2026). Chile: the Coordinador approves each connection (Ley 20.936, art. 79) |
| 2. Commit: what is at risk? | 85% reference, then 75%; data center terms reported only | Brazil: top upfront premium ranks requests, plus a guarantee; missed payment can bar two seasons (Portaria 129/2026). Mexico: guarantees enforced on missed dates (clause 26, Official Gazette). Colombia: the reserve guarantee can be enforced when a load commissions below 90% of assigned capacity (CREG 075/2021, art. 25). Chile: guarantee or prepayment for dedicated-line capacity (art. 80) |
| 3. Price: what does an idle MW cost? | Shortfall charge on monthly peak | No peak-shortfall charge found in the public rules I reviewed |
| 4. Build: who funds the assets? | Upfront connection charge; refundable 25% option at high voltage; operator reportedly pays upgrades (w.media, 12 Nov 2026) | Mexico: private works donated to CFE (Energía Estratégica). Chile, Peru: below |
| 5. Test: what siting or water rule? | Reported water benchmark; Tier 1 and 2 halt | Chile: data centers have no explicit environmental-assessment category and are screened case by case (SEA, Jan 2026). Google’s Cerrillos permit was partly annulled over an aquifer; its air-cooled redesign avoids assessment (El Desconcierto). No water standard found |
Chile and Peru have no data-center rule, but a 500 MW load is not unregulated. General free-client and transmission-charge rules apply.
- Chile. A customer with more than 5,000 kW of connected power is a free client (LGSE art. 147). Under Ley 20.936, applicants pay for reinforcement of dedicated lines (art. 80), and free and regulated consumers pay national and zonal transmission through a charge divided by projected energy billed (art. 115; applied in CNE’s REX 333/2025).
- Peru. Users with annual maximum demand above 2,500 kW are free users (DS 022-2009-EM, art. 3.3). Third parties joining the guaranteed transmission system outside the plan need COES conformity and bear expansion costs. Osinergmin sets secondary and complementary line tolls per unit of energy (DS 018-2016-EM, arts. 62-B, 139; Osinergmin).
I found no charge on undrawn reserved capacity in either country.
Illustration: what 41% means in MW and dollars
My assumptions, not TNB’s costs: $0.8 million of grid cost per MW reserved, carried at 12% a year ($96 per kilowatt-year), all 2,346 MW past ramp-up, constant peak draw, which overstates the gap.
- Unused capacity is 2,346 – 1,374 = 972 MW. At US$0.8 million/MW and 12% annual carrying cost, that implies US$777.6 million in capital and US$93.3 million annually.
- At the same assumed rate, the 85% benchmark (1,994 MW) leaves 620 MW billable: US$59.5 million in hypothetical annual recovery, or 64% of modeled carrying cost. Actual collections depend on each site’s peak and contract terms.
- Scaled to a 500 MW reservation at the same 58.6% draw, 207 MW sits idle, costing US$19.9 million a year. The 85% benchmark yields US$12.7 million recovered and US$7.2 million unrecovered.
This is a scale, not a forecast: at $0.4 to $1.2 million per MW, Malaysia’s 972 MW would be $389 million to $1.17 billion.
What Latin America should copy, and what it should not
- Copy: link speed to commitment, and write the water test first. Brazil’s premium prices a place in line; Malaysia’s shortfall charge prices the draw. Mexico’s donated works move build cost, not under-use risk.
- Do not copy: selling speed first and freezing later, which can delay projects that could meet tighter conditions.
- Watch: Uruguay’s up-to-500 MW Solaria campus began as a 14 October memorandum (SEC filing); on 19 November Solaria reported a 350 MW power purchase agreement with UTE (Solaria). I did not confirm the campus’s own connection terms.
Two asks (my judgment)
- Brazil’s ANEEL, Public Consultation 040/2026, open through 14 December 2026. Consultation 040/2026 implements Law 15.269/2025’s end of network-tariff discounts for consumers who join the free market or enlarge contracted capacity (ANEEL). Specify when each contracted increment loses eligibility and what records establish eligible capacity at the statutory cutoff. That data centers fall under it is my reading.
- Brazil’s MME, consultation 239/2026 on draft transmission grant plan (POTEE) guidelines, open through 30 November 2026 (docket). Require publication of requested, contracted and guaranteed MW for each large-load reinforcement, alongside the existing pre-auction contract requirement where applicable (Portaria 145/2026, art. 2). The consultation does not mention data centers.
Prediction
By 31 December 2027, a regulator or state utility in Brazil, Mexico, Chile, Colombia, Peru or Uruguay will, after an official finding of unused reservations, publish a rule or standard contract charging data centers monthly when actual peak demand falls below a contractual benchmark, as Malaysia’s shortfall charge does. I put it at about one in three; I found none on 24 November 2026. Score a hit if at least one qualifying new monthly shortfall charge follows a dated official finding of unused reservations in the same country by 31 December 2027. Otherwise score a miss. A qualifying rule already in force on 24 November 2026 invalidates the forecast. General charges on measured use do not count.
Limits
- TNB publishes general shortfall terms. Their use in data center agreements rests on press reports. The 60 sen figure is an analyst estimate for a category with separate demand charges, not like-for-like with 45.40 sen.
- The illustration ignores discounting and dedicated-versus-shared grid cost.
- The Latin America column is not a legal review. I read Colombia’s resolutions, Ley 20.936 as printed in 2018 and Peru’s DS 018-2016-EM; later Chilean changes only through CNE’s 2025 resolution. I did not check Peru’s main-grid tolls or connection procedures. For Brazil I relied partly on law-firm and press summaries.
Related Juncture analysis
- Is Your Pending Data-Center Tariff Typical? A 27-Tariff Benchmark
- The Exposure Clock: Who Pays for a Grid Upgrade if the Data Center Never Opens?
- A Study Grant Is Not a Financing Signal: What Atlantico’s Data Center Still Needs
- Who Pays for the Grid? FERC Puts Large-Load Tariffs on a 60-Day Clock
Sources
- Malaysia: The Star, 13 Jul 2026; Malay Mail, 4 Nov 2026; Hansard, 5 Nov 2025; TNB connection charge; TNB shortfall terms; Energy Commission tariff
- Brazil: Decree 12.772/2025; Portaria 129/2026; Portaria 145/2026; ANEEL CP 040/2026; MME CP 239/2026
- Mexico, Colombia, Uruguay: Official Gazette; UPME Res. 443/2026; CREG 075/2021; Solaria
- Chile and Peru: Ley 20.936; CNE REX 333/2025; SEA, Jan 2026; DS 022-2009-EM; DS 018-2016-EM