A study grant is not a financing signal. On 29 September 2026 the US Trade and Development Agency (USTDA) announced an agreement with the Atlantico Governor’s Office to fund technical assistance for a hyperscale data center and fiber optic broadband network in Atlantico, Colombia. According to the Governor’s Office, which announced it on 12 October 2026, the agreement is a non-reimbursable grant of US$1,002,285 for technical, financial and environmental viability studies.
Public sources name no sponsor, firm power, anchor buyer or Commerce designation for Atlantico. The US export-credit route also has a short clock: Commerce’s on-demand window opens on 30 November 2026 and the Export-Import Bank of the United States (EXIM) is scheduled to sunset its authority on 31 December 2026. That is a 31-day window. As of 23 November 2026, the Commerce on-demand phase opens in 7 days and the EXIM sunset is 38 days away. I could not confirm any enacted reauthorization, and the Senate bill, S. 3772, was last reported as referred to the Senate Banking Committee on 4 February 2026. Check congress.gov before relying on this.
This note is for origination staff at USTDA, EXIM, the US International Development Finance Corporation (DFC), the Inter-American Investment Corporation (IDB Invest) and Corporacion Andina de Fomento (CAF), the Development Bank of Latin America and the Caribbean, and for Colombian officials.
What was funded
USTDA says its study will assess technical and financial viability, potential sites, energy capacity and land cost to help mobilize financing. Its release names no US firm, site, power capacity or amount. It says a request for proposals (RFP) will be posted; I could not find it posted. It says US companies carry out USTDA-funded work and states no security conditions for financing.
The Study-to-Term-Sheet Ladder
Juncture’s ladder tracks a project from study to term sheet. A rung counts only on public evidence, and rungs are climbed in order.
| Rung | Test | Atlantico |
|---|---|---|
| 1. Funded | Is preparation money committed? | Green. USTDA agreement, 29 September 2026. |
| 2. Designated | Is the package designated for priority federal financing referrals? | Red. No Colombia or Latin America consortium named. |
| 3. Sponsored | Is a sponsor named, with equity? | Red. No sponsor in any source. |
| 4. Powered | Is firm power contracted? | Red. No connection or supply contract found. |
| 5. Anchored | Does a buyer commit to capacity? | Red. No buyer found. |
| 6. Term sheet | Are permits, currency and security terms settled? | Not reached. |
Atlantico stands on rung 1. The brief’s lender questions map onto the ladder below; colors are Juncture’s judgment.
- Sponsor equity (rung 3): red. The release names no sponsor.
- Power (rung 4): red. No signed connection, supply contract or capacity found. Press reports identify Air-e as a distributor serving Atlantico and date the Superservicios intervention to September 2024.
- Anchor demand (rung 5): red. Colombia’s national artificial intelligence policy, document 4144 (CONPES 4144), approved 14 February 2025, calls for territorial data and computing centers, but a policy is not a purchase commitment.
- Permits and data rules (rung 6): amber. Approvals are not yet mapped. Legal summaries flag cross-border personal data transfers under Law 1581 of 2012.
- Currency (rung 6): amber. Contract and equipment currencies are unknown; assess hedging before term sheets if they differ.
The US financing path and its 31-day clock
Commerce referrals. On 16 November 2026 Commerce announced 33 pre-set consortia offering designated “Super Intelligence” (SI) export packages. Its on-demand phase “will open for applications on November 30, 2026.” Designated packages are eligible for “priority routing for Federal financing referrals.” None is named for Colombia or Latin America.
EXIM. EXIM launched ExportAI on 21 May 2026 (the page now says ExportSI). It offers “more flexible U.S. content requirements when designated by the U.S. Department of Commerce,” but keeps “reasonable assurance of repayment” requirements. The Congressional Research Service (CRS), in its 20 August 2026 report, says Congress renewed the Bank until 31 December 2026 and that after a sunset it “generally could not approve new transactions.” CRS notes Senate bill S. 3772 would extend the sunset by 10 years.
The 31 days. Commerce opens on-demand applications on 30 November. EXIM’s scheduled sunset is 31 December. In my judgment Atlantico cannot use that window: I found no RFP posted, so no study contractor appears selected, and a project with no sponsor has no US exporter to apply.
DFC. DFC’s reauthorization in the fiscal year 2026 National Defense Authorization Act runs through 31 December 2031, with a US$205 billion maximum contingent liability. DFC lists information and communications technology among sectors that can qualify for an exception to geographic restrictions. I found no DFC data center or fiber deal in Colombia.
Multilateral lenders. IDB Invest lists Scala Datacenter Expansion in Brazil as proposed, with a disclosed financing amount of US$150 million, up to US$300 million under consideration and a projected board date of 8 December 2026. It shows IDB Invest finances data centers, not that it will in Colombia. I found no CAF data center loan in Colombia for 2025-2026.
Forward call: Juncture’s recommendation
If no sponsor is publicly named and no USTDA RFP award is made by 31 December 2026, the Atlantico Governor’s Office should route the project toward DFC, IDB Invest or CAF rather than EXIM.
EXIM needs a US exporter, a Commerce designation for its flexible terms and an unexpired charter; Atlantico has no identified exporter or designation, and the charter is scheduled to lapse. DFC’s authority runs five more years after that date. IDB Invest and CAF are not tied to the US charter calendar. I am wrong if a sponsor is named or an award is made before the deadline; revisit if Congress extends EXIM.
Security conditions and a 12-month checklist
Project-specific security terms are not public. I propose for lender discussion: conditions to disbursement (vendor provenance certificate, independent security review, data-governance and government-access policy), covenants (notice of ownership changes, vendor exclusion list, incident notification) and an annual third-party attestation.
My checklist for Atlantico, in ladder order: confirm the study contractor and widen its terms to power, demand and security; name the sponsor and its equity; obtain a written grid connection; collect anchor-demand letters; decide on designation through a US consortium; commission a legal note on permits, data transfers, currency and hedging; sound out DFC, IDB Invest, CAF, EXIM and commercial banks.
What to watch
- 30 November 2026: Commerce on-demand applications open.
- 8 December 2026: projected IDB Invest board date for Scala (a timing marker only).
- 9 December 2026: USTDA’s Latin America broadband business briefing, with Colombian representatives.
- 31 December 2026: scheduled EXIM sunset, and the deadline for the forward call.
- The USTDA RFP, any named sponsor and any Latin American consortium.
Limits
The EXIM sunset date comes from the CRS report of 20 August 2026 and I found no enacted reauthorization; confirm current authority. The full Commerce consortium list and DFC project database were not fully checked, and the Air-e and Law 1581 points rest on secondary sources.
Resumen
En septiembre de 2026, USTDA dio a conocer un acuerdo para financiar un estudio sobre un centro de datos de hiperescala y una red de fibra en Atlantico. Un estudio no es una senal de financiamiento: falta un patrocinador, energia firme y un comprador ancla. La ventana de EXIM es de solo 31 dias.
Related Juncture analysis
- Screening a US AI Export Package in Week One
- EXIM Authority Expires December 31: A Plan for AI Export Packages
- Why U.S. Infrastructure Finance Keeps Losing on Speed
- Sovereign AI Infrastructure Just Found Its Debt Market
- Who Pays for a Grid Upgrade if the Data Center Never Opens?
Sources
- US Trade and Development Agency, “USTDA Funds Secure, AI-Ready Digital Infrastructure in Colombia,” 29 September 2026. https://ustda.gov/ustda-funds-secure-ai-ready-digital-infrastructure-in-colombia/
- Gobernacion del Atlantico, “Gobernacion del Atlantico y la USTDA firman acuerdo para estructurar un Centro de Datos de Hiperescala y ampliar red de fibra optica,” 12 October 2026. https://atlantico.gov.co/index.php/noticias/asuntos-internacionales/28707-gobernacion-del-atlantico-y-la-ustda-firman-acuerdo-para-estructurar-un-centro-de-datos-de-hiperescala-y-ampliar-red-de-fibra-optica
- US Department of Commerce, International Trade Administration, “Department of Commerce Designates SI Export Packages, Announces Next Phase of American SI Exports Program,” 16 November 2026. https://www.trade.gov/press-release/department-commerce-designates-si-export-packages-announces-next-phase-american-si
- Congressional Research Service, “Export-Import Bank: Overview and Reauthorization Debate (IF10017),” 20 August 2026. https://www.everycrsreport.com/files/2026-08-20_IF10017_a26b152b90f8c8aa88824ed41969c1df96d8f803.html
- IDB Invest, “IDB Invest Investor Factsheet,” undated. https://idbinvest.org/en/publications/idb-invest-investor-factsheet
- CAF, “Impact and Allocation Report 2024,” undated. https://www.caf.com/media/4681160/impact-and-allocation-report-2024.pdf
- Noticias RCN, “Superservicios tomo posesion de la empresa Air-e, en Barranquilla,” 12 September 2024. https://www.noticiasrcn.com/colombia/superservicios-tomo-posesion-de-air-e-en-barranquilla-747544
- El Heraldo, “Mientras Superservicios defiende sus acciones para estabilizar Air-e, Norman Alarcon cuestiona sus resultados,” 30 July 2026. https://www.elheraldo.co/atlantico/2026/07/30/superservicios-afirma-que-ha-adelantado-mas-de-20-acciones-para-estabilizar-financieramente-a-air-e/
- Departamento Nacional de Planeacion (DNP), “CONPES 4144: La hoja de ruta de Colombia en Inteligencia Artificial para los retos actuales y la transformacion futura,” 16 May 2025. https://dnp.gov.co/publicaciones/Planeacion/Paginas/conpes-4144-hoja-de-ruta-colombia-inteligencia-artificial-retos-actuales-transformacion-futura.aspx
- Congreso de la Republica de Colombia (Secretaria del Senado), “Ley 1581 de 2012, por la cual se dictan disposiciones generales para la proteccion de datos personales,” 17 October 2012. http://www.secretariasenado.gov.co/senado/basedoc/ley_1581_2012.html
- Export-Import Bank of the United States, “EXIM Launches ExportAI Initiative to Strengthen American Leadership in AI,” 21 May 2026. https://exim.gov/news/exim-launches-exportai-initiative-strengthen-american-leadership-ai
- Export-Import Bank of the United States, “Export SI Initiative,” accessed 23 November 2026. https://www.exim.gov/about/special-initiatives/export-si-initiative
- US International Development Finance Corporation, “DFC Secures Expanded Authorities with FY26 NDAA Signed into Law,” 18 December 2025. https://www.dfc.gov/media/press-releases/dfc-secures-expanded-authorities-fy26-ndaa-signed-law
- US International Development Finance Corporation, “Where We Work,” accessed 23 November 2026. https://www.dfc.gov/what-we-offer/work-with-us/where-we-work
- IDB Invest, “Scala Datacenter Expansion,” 25 September 2026. https://idbinvest.org/en/projects/scala-datacenter-expansion
- US Trade and Development Agency, “Latin America and the Caribbean,” accessed 23 November 2026. https://ustda.gov/regions/latin-america-and-the-caribbean/